Many new and exciting things are happening in Plum Creek, and here’s a brief overview of some of the accomplishments from March, as well as the projects we have coming up.

Completed:

  • Repair to lake deck.
  • Annual backflow testing.
  • Community Center attic ladder repair.
  • Misc. irrigation repairs in Master & Peninsula.
  • Maintenance and repair for 6H pedestrian gates.
  • Deck drainage replacement at Haupt.
  • Updated technology installed for gate access at pools and 6H.
  • Coffee with the CAM on Friday, March 13th.

In Progress/Upcoming:

  • Coffee with the CAM 4-10-26.
  • Preparation for the Annual Meeting on 4-28-26.
  • Preparations for pool season, finalizing projects, legal signage, etc.
  • New pool furniture ordered for both pools. Delivery date TBD.
  • Pool shade replacements ordered for both pools. Delivery date TBD.
  • Collaboration with the board on revising the private street parking rules.
  • Continued planning and research on inclusive swing set options for parks.
  • Continued planning and research for new Community Center furniture.
  • Bids gathered for lake remediation. Will be put before the board for discussion.
  • Continued website refinement for improved resident satisfaction.
  • Preparation for additional cameras to be installed for both pools.
  • Preparation for new camera systems to be installed at the Peninsula gates.
  • Updates to the ARC application and process.